Notice: Function Elementor\Core\Experiments\Manager::warn_removed_or_hidden_dependency was called incorrectly. Feature mega-menu depends on hidden experiment nested-elements. Please see Debugging in WordPress for more information. (This message was added in version 4.3.5.) in /home/u740374097/domains/diligentia.net.in/public_html/wp-includes/functions.php on line 6131
IOC’s Paradip-Hyderabad pipeline project to end by Dec 2023 – Diligentia Services

IOC’s Paradip-Hyderabad pipeline project to end by Dec 2023

The Paradip-Hyderabad Pipeline Project (PHPL) by Indian Oil Corporation Ltd. (IOCL) will likely be operational by the end of next year.

Speaking to the media, IOCL executive director and Head for AP and Telangana, B. Anil Kumar said that the business will invest Rs 33.38 billion to carry out this project for improved fuel deliveries to its retail outlets in three states

This project connects the Hyderabad refinery in Telangana to the Paradip refinery in Odisha via Andhra Pradesh.

Although PHPL was expected to be operational by 2020, land acquisition issues delayed its progress

Anil Kumar also said that almost 87 percent of the construction is complete, and the works are going on in full swing adding that it shall be commissioned by December 2023.